Prepare the Foundation & Fix the Keel
Harden the ground, set out the keel grid, then anchor it with expansion screws.
To install the flooring, the fundamental ground floor must be hardened first. Then fix the keel to the hardened ground with expansion screws.
Keep the spacing between two keels at L ≤ 350 mm — this can be adjusted slightly according to site conditions, but never widened beyond 350 mm for standard residential use.
- Check the ground for level before laying any keel
- Keep 3–5 mm clearance where the keel meets the building
- Drive expansion screws at 400–500 mm centres
- Pre-drill 70 mm from the board end to avoid splitting